production plant

Sennheiser electronics

Germany, Wennebostel, execution 2008 – 2009

concept

Two storey plant with offices for the development and fabrication areas for the production of electrical components.
The floor plan and section design primary follow aspects of adaptation and communication. 




Image

structure

Precast concrete parts built up the main structure with an supporting grid of 16.80 m x 8.40 m.
Along the exterior walls galleries are clamped between the concrete columns to house office and sanitary spaces.
Two pedestrian passages connect those galleries with the existing plant structures on the site. 



facts

10,800 m² gross floor area
67,000 m³ gross volume

Image
Image